Multi-factor dependence modelling with specified marginals and structured association in large-scale project risk assessment. (English) Zbl 1490.90005

Summary: This paper examines the high-dimensional dependence modelling problem in the context of project risk assessment. As the dimension of uncertain performance units (i.e., itemized costs and activity times) in a project increases, specifying a feasible correlation matrix and eliciting relevant pair-wise information, either from historical data or with expert judgement, becomes practically unattainable or simply not economical. This paper presents a factor-driven dependence elicitation and modelling framework with scalability to large-scale project risks. The multi-factor association model (MFAM) accounts for hierarchical relationships of multiple association factors and provides a closed-form solution to a complete and mathematically consistent correlation matrix. Augmented with the structured association (SA) technique for systematic identification of hierarchical association factors, the MFAM offers additional flexibility of utilizing the minimum information available in standardized, ubiquitous project plans (e.g., work breakdown structure, resource allocation, or risk register), while preserving the computational efficiency and the scalability to high dimensional project risks. Numerical applications and simulation experiments show that the MFAM, further combined with extended analytics (i.e., parameter calibration and optimization), provides credible risk assessments (with accuracy comparable to full-scale simulation) and further enhances the realism of dealing with high-dimensional project risks utilizing all relevant information.

MSC:

90-10 Mathematical modeling or simulation for problems pertaining to operations research and mathematical programming
90B35 Deterministic scheduling theory in operations research
90B50 Management decision making, including multiple objectives

Software:

ROME; Bolstad
PDFBibTeX XMLCite
Full Text: DOI

References:

[1] Asadabadi, M. R.; Zwikael, O., Integrating risk into estimations of project activities’ time and cost: A stratified approach, European Journal of Operational Research, 291, 2, 482-490 (2021) · Zbl 1487.90265
[2] Baccarini, D., The concept of project complexity—A review, International Journal of Project Management, 14, 4, 201-204 (1996)
[3] Bedford, T.; Cooke, R. M., Vines: A new graphical model for dependent random variables, Annals of Statistics, 30, 4, 1031-1068 (2002) · Zbl 1101.62339
[4] Bolstad, W. M., Introduction to Bayesian statistics (2007), John Wiley & Sons, Inc.: John Wiley & Sons, Inc. Hoboken, New Jersey · Zbl 1136.62023
[5] Cario, M. C.; Nelson, B. L., Modeling and generating random vectors with arbitrary marginal distributions and correlation matrix (1997), Department of Industrial Engineering and Management Sciences, Northwestern University: Department of Industrial Engineering and Management Sciences, Northwestern University Evanston, IL
[6] Chau, K. W., Monte Carlo simulation of construction costs using subjective data, Construction Management & Economics, 13, 5, 369 (1995)
[7] Cho, S., A linear Bayesian stochastic approximation to update project duration estimates, European Journal of Operational Research, 196, 2, 585-593 (2009) · Zbl 1163.90680
[8] Clemen, R. T.; Fischer, G. W.; Winkler, R. L., Assessing dependence: Some experimental results, Management Science, 46, 8, 1100-1115 (2000) · Zbl 1232.91543
[9] Cohen, J., Statistical power analysis for the behavioral sciences, (1988), Routledge · Zbl 0747.62110
[10] Demirtas, H.; Hedeker, D., A practical way for computing approximate lower and upper correlation bounds, The American Statistician, 65, 2, 104-109 (2011) · Zbl 1297.97031
[11] Fallat, S. M.; Johnson, C. R., Hadamard powers and totally positive matrices, Linear Algebra and its Applications, 423, 2-3, 420-427 (2007) · Zbl 1123.15014
[12] Flyvbjerg, B., From Nobel prize to project management: Getting risks right, Project Management Journal, 37, 3, 5-15 (2006)
[13] GAO Schedule assessment guide: Best practices for project schedules, Applied research and methods, 240 (2015), U.S. Government Accountability Office (GAO): U.S. Government Accountability Office (GAO) Washington, DC
[14] GAO Cost estimating and assessment guide: Best practices for developing and managing capital program costs, Applied research and methods (2020), U.S. Government Accountability Office (GAO): U.S. Government Accountability Office (GAO) Washington, DC
[15] Garvey, P. R.; Book, S. A.; Covert, R. P., Probability methods for cost uncertainty analysis: A systems engineering perspective (2016), CRC Press
[16] Ghosh, S.; Henderson, S. G., Behavior of the NORTA method for correlated random vector generation as the dimension increases, ACM Transactions on Modeling and Computer Simulation (TOMACS), 13, 3, 276-294 (2003) · Zbl 1390.65009
[17] Goh, J.; Sim, M., Robust optimization made easy with ROME, Operations Research, 59, 4, 973-985 (2011) · Zbl 1235.90107
[18] Hertz, D. B., Risk analysis in capital investment, Harvard Business Review, 42, 1, 95-106 (1964)
[19] Hulett, D. T., Integrated cost-schedule risk analysis (2011), Gower Publishing, Ltd
[20] Kim, B.-C. P.; Jeffrey, K., What CPI = 0.85 really means: A probabilistic extension of the estimate at completion, ASCE Journal of Management in Engineering, 35, 2, 1-18 (2019)
[21] Kim, B.-. C., Integrating risk assessment and actual performance for probabilistic project cost forecasting: A second moment Bayesian model, IEEE Transactions on Engineering Management, 62, 2, 158-170 (2015)
[22] Kim, B.-. C., Dependence modeling for large-scale project cost and time risk assessment: Additive Risk factor approaches, IEEE Transactions on Engineering Management (2021)
[23] Kim, B.-. C.; Kwak, Y. H., Improving the accuracy and operational predictability of project cost forecasts: An adaptive combination approach, Production Planning & Control, 29, 9, 743-760 (2018)
[24] Kurowicka, D.; Cooke, R. M., Uncertainty analysis with high dimensional dependence modelling (2006), John Wiley & Sons · Zbl 1096.62073
[25] Love, P.; Sing, C.; Wang, X.; Edwards, D. J.; Odeyinka, H., Probability distribution fitting of schedule overruns in construction projects, Journal of the Operational Research Society, 64, 8, 1231-1247 (2013)
[26] Love, P.; Wang, X.; Sing, C.; Tiong, R., Determining the probability of project cost overruns, Journal of Construction Engineering and Management, 139, 3, 321-330 (2013)
[27] Lurie, P. M.; Goldberg, M. S., An approximate method for sampling correlated random variables from partially-specified distributions, Management Science, 44, 2, 203-218 (1998) · Zbl 1103.62322
[28] Malcolm, D. G.; Roseboom, J. H.; Clark, C. E.; Fazar, W., Application of a technique for research and development program evaluation, Operations Research, 7, 5, 646-669 (1959) · Zbl 1255.90070
[29] Mo, J.; Yin, Y.; Gao, M., State of the art of correlation-based models of project scheduling networks, IEEE Transactions on Engineering Management, 55, 2, 349-358 (2008)
[30] Morgan, M. G.; Henrion, M.; Small, M., Uncertainty: A guide to dealing with uncertainty in quantitative risk and policy analysis (1992), Cambridge University press
[31] Morris, P. W., Reconstructing project management (2013), John Wiley & Sons
[32] Analytic method for probabilistic cost and schedule risk analysis (2013), National Aeronautics and Space Administration (NASA): National Aeronautics and Space Administration (NASA) Washington, DC
[33] Newton, S., Methods of analysing risk exposure in the cost estimates of high quality offices, Construction Management & Economics, 10, 5, 431-449 (1992)
[34] Palmer, C.; Urwin, E. N.; Niknejad, A.; Petrovic, D.; Popplewell, K.; Young, R. I., An ontology supported risk assessment approach for the intelligent configuration of supply networks, Journal of Intelligent Manufacturing, 29, 5, 1005-1030 (2018)
[35] A guide to the project management body of knowledge (2013), Project Management Institute, Inc.: Project Management Institute, Inc. Newtown Square, PA
[36] Ranasinghe, M., Impact of correlation and induced correlation on the estimation of project cost of buildings, Construction Management & Economics, 18, 4, 395-406 (2000)
[37] Reinschmidt, K. F., P, roject risk management: Class notes (2009), Zachry Department of Civil Engineering, TXTexas A&M University, College Station
[38] Rodger, J. A., A fuzzy linguistic ontology payoff method for aerospace real options valuation, Expert Systems with Applications, 40, 8, 2828-2840 (2013)
[39] Safran (2020). “Pacific Northwest National Laboratory (PNNL)”. https://www.safran.com/case-studies/pacific-northwest-national-laboratory?hsCtaTracking=deabe776-2577-43d0-bb60-2096ab40a608
[40] Scheuer, S.; Haase, D.; Meyer, V., Towards a flood risk assessment ontology-Knowledge integration into a multi-criteria risk assessment approach, Computers, Environment and Urban Systems, 37, 82-94 (2013)
[41] Schonberger, R. J., Why projects are “always” late: A rationale based on manual simulation of a PERT/CPM network, Interfaces, 11, 5, 66-70 (1981)
[42] Skitmore, M.; Ng, S., Analytical and approximate variance of total project cost, Journal of Construction Engineering and Management, 128, 5, 456-460 (2002)
[43] Song, J.; Martens, A.; Vanhoucke, M., Using schedule risk analysis with resource constraints for project control, European Journal of Operational Research, 288, 3, 736-752 (2021) · Zbl 1487.90325
[44] Styan, G. P., Hadamard products and multivariate statistical analysis, Linear Algebra and its Applications, 6, 217-240 (1973) · Zbl 0255.15002
[45] Tatikonda, M. V.; Rosenthal, S. R., Technology novelty, project complexity, and product development project execution success: A deeper look at task uncertainty in product innovation, IEEE Transactions on Engineering Management, 47, 1, 74-87 (2000)
[46] Touran, A.; Wiser, E. P., Monte Carlo technique with correlated random variables, Journal of Construction Engineering and Management, 118, 2, 258-272 (1992)
[47] Trietsch, D., The effect of systemic errors on optimal project buffers, International Journal of Project Management, 23, 4, 267-274 (2005)
[48] Trietsch, D.; Mazmanyan, L.; Gevorgyan, L.; Baker, K. R., Modeling activity times by the Parkinson distribution with a lognormal core: Theory and validation, European Journal of Operational Research, 216, 2, 386-396 (2012)
[49] van Dorp, J. R., Statistical dependence through common risk factors: With applications in uncertainty analysis, European Journal of Operational Research, 161, 1, 240-255 (2005) · Zbl 1067.90122
[50] van Dorp, J. R., A dependent project evaluation and review technique: A Bayesian network approach, European Journal of Operational Research, 280, 2, 689-706 (2020) · Zbl 1430.90294
[51] Van Slyke, R. M., Monte Carlo methods and the PERT problem, Operations Research, 11, 5, 839-860 (1963)
[52] Wang, C.-. H.; Huang, Y.-. C., A new approach to calculating project cost variance, International Journal of Project Management, 18, 2, 131-138 (2000)
[53] Werner, C.; Bedford, T.; Cooke, R. M.; Hanea, A. M.; Morales-Nápoles, O., Expert judgement for dependence in probabilistic modelling: A systematic literature review and future research directions, European Journal of Operational Research, 258, 3, 801-819 (2017) · Zbl 1394.90368
[54] Williams, T. M., The need for new paradigms for complex projects, International Journal of Project Management, 17, 5, 269-273 (1999)
[55] Williams, T. M., The contribution of mathematical modelling to the practice of project management, IMA Journal of Management Mathematics, 14, 1, 3-30 (2003) · Zbl 1134.90430
[56] Xing, X.; Zhong, B.; Luo, H.; Li, H.; Wu, H., Ontology for safety risk identification in metro construction, Computers in Industry, 109, 14-30 (2019)
This reference list is based on information provided by the publisher or from digital mathematics libraries. Its items are heuristically matched to zbMATH identifiers and may contain data conversion errors. In some cases that data have been complemented/enhanced by data from zbMATH Open. This attempts to reflect the references listed in the original paper as accurately as possible without claiming completeness or a perfect matching.