Fuzzy-probabilistic PERT. (English) Zbl 1381.90048

Summary: Using PERT (Program evaluation and review technique), one assumes that the time required to carry out the individual tasks in a project can be approximated using a beta distribution. It is assumed that the parameters of these distributions (the minimum, maximum and most likely times) are estimated by experts in accordance with the properties of the beta distribution. However, this is not always the case. This article shows how one may analyse the time required to carry out a task. Two approaches to describing uncertainty regarding the duration of tasks are used: probabilistic and fuzzy. This article proposes a mixture of a beta probability distribution with a generative probability distribution to describe the duration of a task. Illustrative examples are given.

MSC:

90B70 Theory of organizations, manpower planning in operations research
PDFBibTeX XMLCite
Full Text: DOI

References:

[1] Abdelkader, Y. H. (2004). Evaluating project completion times when activity times are Weibull distribution. European Journal of Operational Research, 157, 704-715. · Zbl 1067.90037 · doi:10.1016/S0377-2217(03)00269-8
[2] Abdelkader, Y. H. (2010). Adjustment of the moments of the project completion times when activity times are exponentially distributed. Annals of Operations Research, 181, 503-514. · Zbl 1209.90072 · doi:10.1007/s10479-010-0781-3
[3] Chen, C. T., & Huang, S. F. (2007). Applying fuzzy method for measuring criticality in project network. Information Sciences, 177, 2448-2458. · Zbl 1124.90013 · doi:10.1016/j.ins.2007.01.035
[4] Chen, S. P., & Hsueh, Y. J. (2008). A simple approach to fuzzy critical path analysis in project networks. Applied Mathematical Modelling, 32, 1289-1927. · Zbl 1172.90333 · doi:10.1016/j.apm.2007.04.009
[5] Chanas, S., & Nowakowski, M. (1988). Single value simulation of fuzzy variable. Fuzzy Sets and Systems, 25, 43-57. · Zbl 0633.65144 · doi:10.1016/0165-0114(88)90098-X
[6] Chrysafis, K. A., & Papadopoulos, B. K. (2015). Possibilistic moments for the task duration in fuzzy PERT. Journal of Management in Engineering, 31(5), 04014071. · doi:10.1061/(ASCE)ME.1943-5479.0000296
[7] Chrysafis, K. A., & Papadopoulos, B. K. (2014). Approaching activity duration in PERT by means of fuzzy sets theory and statistics. Journal of Intelligent and Fuzzy Systems, 26(2), 577-587. · Zbl 1305.62390
[8] Chrysafis, K. A., Panagiotakopoulos, D., & Papadopoulos, B. K. (2013). Hybrid (fuzzy-stochastic) Modelling in Construction Operations Management. International Journal of Machine Learning & Cybernetics, 4(4), 339-346. · doi:10.1007/s13042-012-0093-9
[9] Dubois, D., Fortin, J., & Zieliński, P. (2010). Interval PERT and its fuzzy extension. In C. Kahraman & M. Yavuz (Eds.), Production engineering and management under fuzziness. Studies in fuzziness and soft computing (Vol. 252, pp. 171-199). Berlin: Springer. · Zbl 1198.90230
[10] Dubois, D., & Prade, H. (1988). Possibility theory: An approach to computerized processing of uncertainty: Plenum Press. · Zbl 0703.68004
[11] Gallagher, C. (1987). A note on PERT assumptions. Management Science, 33, 1360-1360. · doi:10.1287/mnsc.33.10.1360
[12] Gan, L., & Xu, J. (2015). Control risk for multimode resource-constrained project scheduling problem under hybrid uncertainty. Journal of Management in Engineering, 31(3), 1-16. doi:10.1061/(ASCE)ME.1943-5479.0000243. · Zbl 1209.90072
[13] Garcia, C. B. G., Perez, J. G., & Rambaud, S. C. (2010). Proposal of new distribution in PERT methodology. Annals of Operations Research, 181, 515-538. · Zbl 1254.90081 · doi:10.1007/s10479-010-0783-1
[14] Gładysz, B. (2014) Mixtures of fuzzy variables in the analysis of a project’s duration a robust approach. Proceedings of XIII Conference Polish Operational and Systems Research Society: Advances and Experiences, Warsaw, 24-26.09.2014, IBS, Warsaw, 1-7 · Zbl 0804.90052
[15] Golenko, D. I. (1989). A new approach to the activity-time distribution in PERT. Journal of Operational Research Society, 40, 389-393. · Zbl 0666.90034 · doi:10.1057/jors.1989.57
[16] Grubbs, F. (1962). Attempts to validate PERT statistics or picking on PERT. Operations Research, 10, 912-915. · doi:10.1287/opre.10.6.912
[17] Hahn, E. (2008). Mixture densities for project management activity times: A robust approach to PERT. European Journal of Operational Research, 210, 450-459. · Zbl 1149.90351 · doi:10.1016/j.ejor.2007.04.032
[18] Herreras-Velasco, J., Herreras-Pleguezuelo, R., & Dorp, J. (2011). Revisiting the PERT mean and variance. European Journal of Operational Research, 210(2), 448-454. · Zbl 1210.90103 · doi:10.1016/j.ejor.2010.08.014
[19] Kamburowski, J. (1997). New validation of PERT times. Omega The International Journal of Management Science, 25(3), 323-328. · doi:10.1016/S0305-0483(97)00002-9
[20] Magott, J., & Skudlarski, K. (1993). Estimating the mean completion time of PERT networks with exponentially distributed duration of activities. European Journal of Operational Research, 71(1), 70-79. · Zbl 0804.90052 · doi:10.1016/0377-2217(93)90261-K
[21] Malcolm, D., Rosenboom, J., Clark, C., & Fazar, W. (1959). Application of a technique for research and development program evaluation. Operations Research, 7, 646-669. · Zbl 1255.90070 · doi:10.1287/opre.7.5.646
[22] Pour, N., Kheranmand, M., Fallah, M., & Zeynali, S. (2011). A new method for critical path method with fuzzy processing time. Management Sciences Letters, 1, 347-354. · doi:10.5267/j.msl.2011.22.003
[23] Shankar, N., Sireesha, V., & Rao, B. (2010). An analytical method for finding critical path in a fuzzy project network. International Journal of Contemporary Mathematical Sciences, 5(20), 953-962. · Zbl 1230.90049
[24] Zadeh, L. (1968). Probability measures of fuzzy events. Journal of Mathematical Analysis and Applications, 23, 421-427. · Zbl 0174.49002 · doi:10.1016/0022-247X(68)90078-4
This reference list is based on information provided by the publisher or from digital mathematics libraries. Its items are heuristically matched to zbMATH identifiers and may contain data conversion errors. In some cases that data have been complemented/enhanced by data from zbMATH Open. This attempts to reflect the references listed in the original paper as accurately as possible without claiming completeness or a perfect matching.